Normally, the planned order determined the date from Material Master. The Planned Order created by the MRP reads the production capacity requirement from Material Master. (MM03 – Work Scheduling – Lot size dependent in-house production time). When you convert the planned order to a production order, SAP determined the date from Routing.
User Requirements:- Planned and Production Order should read the requirement from routing.
Solutions:-
Run MRP Scheduling -> 2 – Lead time scheduling and capacity planning
Transaction OPA9 (Sel. Profile - SAPA010) - Change configuration for Capacity Planning to read Production Order. Untick the Planned orders under the Order categories.