Q: How can we shut off the "automatic costing indicator" and the "automatic scheduling indicator" which go on when the production order is released?
A: For "no automatic costing" follow the IMG path
Production -> Production orders ->Master data -> Order - >Define order type dependent parameters
Select the order type for which u automatic costing is not required. In the controlling settings, select "no automatic costing"
For "no automatic scheduling" , follow the IMG path :
Production ->Operations - >Scheduling -> Define control parameters
Select the order type and go to details. Deselect " automatic dates "
Alternatively, you can find indicators in the control key, which is in the routing. Transaction OPL8 gives you costing indicators (Order type dependent parameters), and OPJU (control table for scheduling) gives some scheduling options.
Friday, September 12, 2008
Subscribe to:
Post Comments (Atom)
Archive
-
▼
2008
(75)
-
▼
September
(62)
- Free Download SAP PP Certification Study pdf books
- In PP,Mass Delete Planned Order
- In PP,Firmed Planned Orders, What is its use in Pr...
- In PP,Difference Between Planned & Prod. Orders
- In PP,BOM components never explode
- In PP,BOM Display Changes
- In PP,Configure Phantom assembly
- In PP,The Concept (use) of Phantom Assembly
- In PP,Work Center Creation and Change
- In PP,Configuring an Additional Activity Type
- In PP,Total Plan Activities in Minutes
- In PP,To compare multiple BOMs
- In PP,Long Term Planning BOM Selection
- In PP,Attach The Components Drawing In a BOM
- Interface Settings PP
- PP Faqs -II
- Bills Of Material PP
- Work Centers PP
- Routing - III
- Routing - II PP
- Routing - I PP
- Sales & Operations Planning PP
- Demand Management PP
- M R P - IV PP
- M R P - III PP
- M R P - II PP
- M R P - I PP
- Production Orders-IX PP
- Production Orders-VIII PP
- Production Orders--VII PP
- Production Orders-VI PP
- Production Orders-V PP
- Production Orders-IV PP
- Production Orders-II PP
- Production Orders-III PP
- Production Orders-I PP
- variable size PP
- Creating a Configuration Profile
- Class Assignment
- Filters for BOM Explosion
- Availability of Components PP
- Changing/Displaying/Deleting Configuration Profiles
- Possible Combinations of Configuration Profiles
- BOM PP
- Control whether the Production Order operations wi...
- Determine whether Planned / Production Order are i...
- Super BOM
- Selecting BOM Items
- Classification as a Selection Condition
- Selection from a Class Item
- Selection from a Class Item: Example
- Finding Objects in a Class Item
- Variant Classes
- Defining Classes as BOM Items
- The Configuration Profile
- Controlling the BOM Explosion in PP
- Single-Level BOM Explosion
- Multi-Level BOM Explosion
- Modular BOM
- Writing a Multi-Level BOM Cost Roll-up with ABAP
- Sample ABAP on Multi-Level Bom with Location Balance
- Bill of materials
-
▼
September
(62)
No comments:
Post a Comment